I wanted to check on the present CAISO interconnection queue status for PV projects that were submitted in the Cluster #5 window.  This was the submission for the March 2012 Cluster #5  window.  These are for interconnection onto the CAISO controlled transmission line systems of SCE/PG&E/SDG&E.  Some additional 20MW projects, especially in SCE territory, would be on their WDAT interconnection queue as they have some lines at the 70Kv level designated as part of their distribution network.

As of the end of October my calculations were as follows:

  • 3.8GW of solar PV is still in the queue waiting for the phase 1 study results and the deposits needed then
  • 2.7GW of solar has already dropped out at this time

There are many developer/investor groups that would think these cluster #5 projects are too late for any reality until much after 2016, so it is still amazing to see so much still alive.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Categories

%d bloggers like this: